Orange
Water and Sewer Authority
400 JONES FERRY
ROAD
CARRBORO NC 27510
Telephone: (919) 968-4421 or E-mail: OWASA
January 17, 2006 Mr. W. Calvin Horton, Town Manager Dear Cal: In accord with the Special Use Permit for the Mason Farm Wastewater Treatment Plant, we are pleased to submit the enclosed annual report on our progress toward our off-site odor elimination goal and in the overall improvements underway at the plant. The attached report essentially updates the progress report which we submitted at the Town Council’s public forum on November 14, 2005. Please note that the attached report refers to but does not include the Odor Elimination Compliance Monitoring Program which we previously submitted to the Town. Some key items in the attached report include:
We remain committed to working with our customers and the Town to achieve results that will be fully satisfactory to the community. We sincerely hope that this process will prove to be a model example of wastewater odor control with open, effective public participation that benefits all parties. Sincerely, Ed Kerwin C: OWASA Board of Directors |
January 17, 2006
Introduction This annual report is submitted in accord with conditions in the Special Use Permit as modified by the Town Council on March 1, 2004 for the Mason Farm Wastewater Treatment Plant (WWTP). The special use permit includes the following requirement:
Actions and Improvements in 2005 Odor-related improvements Digester covers: Our contractor completed the installation of new cover structures on the four “solids digesters” at the WWTP in late November, 2005 in accord with our original project timetable. (Our “solids digesters” are tanks where solids separated from wastewater are converted into biosolids for reuse on farms to help grow crops for non-human consumption.) The first two of the new digester cover structures were installed in 2004. In 2005, the two remaining digesters received new covers and one of the previously installed new covers was repaired in the fall after leaks were found. We believe the digester cover improvements, which cost about $3.5 million, were a significant step forward in reducing odor releases. The covers were originally installed with a circumferential gap that enabled the covers to slide up and down as needed during biosolids treatment, but the gap also allowed releases of odor. The new digester covers are fixed and they have a perimeter seal to contain foul air in the digester tanks for transport through pipes for burning as fuel or for disposal.
Number of reports of odor releases from the WWTP The table below shows the number of reports of odor from the WWTP from 2002 through 2005. Several customers have informally reported to us that odor conditions improved as the installation of digester covers progressed over the last year or so. However, odor reports from citizens increased in November and December, 2005 due to malfunctions in the system of “gas handling” pipes that carry foul air away from the digesters for use or disposal. We identified these pipes as an additional odor source in the late fall and are planning to renovate or replace them in 2006. REPORTS OF ODOR FROM THE MASON FARM WASTEWATER TREATMENT PLANT,
Communications with our neighbors and the Town of Chapel Hill Community Meeting: On September 15th we held a community meeting to discuss a draft Odor Elimination Compliance Monitoring Program with our neighbors. We invited more than 700 people to this meeting by e-mail and paper mailings. A summary is attached. The OWASA Board approved the Compliance Monitoring Plan, with changes reflecting feedback we received from stakeholders, in a public meeting on October 13, 2005. Town Council’s Public Forum: On November 14th, we made a presentation to the Town Council and the community in a televised public forum on our progress in eliminating odor releases from the WWTP. We reported that completion of the digester cover installations was pending, additional odor elimination work is needed and we will do an odor study beginning in 2006 in consultation with stakeholders. We also presented the Odor Elimination Compliance Monitoring Program. In accord with the Council’s decisions at the end of the public forum, we will work with stakeholders in the WWTP area to draft an operational definition to clarify the practical meaning of “odor elimination.” We appreciate the recognition by the Town and other stakeholders that perfect odor elimination is not practical although it continues to be our goal. In addition, we will include updates about the WWTP improvements and odor-related matters, including tabulations of odor reports from the community, in our future quarterly reports to the Towns of Chapel Hill and Carrboro and Orange County. Upcoming Actions Next community meeting We will meet with interested stakeholders to discuss planning the odor study and related matters on Tuesday night, January 31st, 2006 at 7:00 pm in the OWASA Community Room. The primary purpose of this meeting will be to enable citizens to meet and talk with our odor consultant and OWASA staff about what the study should accomplish, how it will be done and how citizens should be involved and informed during the study process. We want to involve stakeholders at this early stage, before the scope of work for the odor study has been prepared, with the objective of reaching consensus on how it will proceed and what it will provide when complete. At the community meeting, we will also discuss developing an operational definition of odor elimination as a follow up to comments from citizens and the Town Council’s discussion in November. Gas handling system improvements As discussed above, we recently identified the pipes that carry foul air away from our solids digesters as an odor source and we plan to rework or replace them in 2006. Design work has begun and it should be complete this winter in preparation for the contracting process. The work may take 6 to 9 months, depending on the specific scope of work, weather conditions and so forth. Unfortunately, some temporary releases will likely be necessary during the construction. Plant improvements under contract for completion by 2007 As indicated in previous reports, the odor-related improvements scheduled to be completed at the WWTP by May, 2007 include:
Conclusion We welcome the opportunity to receive comments and respond to any questions about this report or the Mason Farm Wastewater Treatment Plant improvement project and our odor elimination plans. We look forward to making further progress in the odor elimination program and continuing our discussions with customers in the area around the Mason Farm Wastewater Treatment Plant and with the Town. Attachments:
|
Attachment 1 SUMMARY OF COMMUNITY MEETING regarding odor elimination at the Mason Farm Wastewater Treatment Plant and 7:00 pm, Thursday, September 15, 2005, in the Community Room, Participants Barnes Bierck, 3 Hampton Hill Place, Chapel Hill OWASA Randolph M. Kabrick, P.E., Secretary, OWASA Board Introduction Ed Kerwin welcomed the citizens and said that the meeting’s primary purpose was to receive feedback about a draft plan for monitoring and evaluating odor at the Mason Farm Wastewater Treatment Plant (WWTP) after scheduled completion of odor-related improvements to four solids digesters by the end of November, 2005. Mr. Kerwin presented a map of key facilities in the WWTP site and reviewed odor control improvements at the plant in recent years. Summary of Comments by Citizens Notes: Comments below are paraphrased and not in actual order. This summary focuses on comments received from citizens; OWASA staff’s responses to questions below are intentionally not included.) Summary of Community Meeting on September 15, 2005
|
Attachment 2 ADDITIONAL BACKGROUND INFORMATION ABOUT ODOR ELIMINATION Need for and planning of the WWTP improvements In 2002, following several discussions, the OWASA Board of Directors decided to move forward with a project to:
In May, 2004, a three-year, $50 million improvement project began at the WWTP in accord with the Town Council’s approval of a special use permit in March, 2004 as noted above. This improvement project is financed primarily from bonds. Public communications and discussions In 2002, we began making operating and maintenance changes to achieve short-term reductions in off-site odor and planning the more extensive capital improvements needed to resolve the odor releases for the longer term, and we began a communication process with stakeholders. Starting in March, 2002 we held several meetings with homeowners’ organizations in Highland Woods and Hunt’s Reserve, and began providing information and periodic updates to customers in the areas where odor was reported. In part, we encouraged customers to report odor when they noticed it at any time of day so that we could promptly investigate to determine and address the source of the odor. On March 1, 2004, the OWASA Board of Directors formally established a goal of having no off-site objectionable odors at the WWTP. (The resolution adopting this goal was submitted to the Town Council that night for consideration with the WWTP Special Use Permit modification.) In April, 2004, we held a community meeting to discuss plans for the WWTP improvements including odor elimination work and plans for an odor study and evaluation process with stakeholders following completion of the new digester covers in November, 2005. In May, 2004, we established and publicized a 24-hour Hotline, 537-4376, for citizens to report odor and check the status of the WWTP improvement project. We continue to provide mail and e-mail project updates and notices to customers about the conditions such as temporary odor releases due to construction and work involving noise, additional traffic, etc. Odor-related facility improvements and related actions from 2002 to 2004 at the WWTP
|
|||||||||||||||||
Home | Water System | Wastewater | Customer Service | Plans | Contact Us | Site Map