|
Water
Supply: A 50-Year Vision for The Community
Executive
Summary
OWASA withdraws
an average of 9 million gallons per day (mgd) of water
from the Cane Creek/University Lake/Quarry Reservoir
system. Customer demands are expected to exceed the
raw water systems safe yield of 11.2 mgd by 2010.
The present reservoir/quarry system receives sufficient
streamflow and has enough storage capacity to support
an average yield of 15 mgd, but is presently constrained
by limitations of the infrastructure to move additional
raw water from the reservoirs to the Jones Ferry Road
Water Treatment Plant in Carrboro.
The present
safe yield can be increased to 15 mgd through improvements
to the conveyance system, such as larger raw water transmission
pumps and pipelines from University Lake and Cane Creek
to the water plant. Costs for these upgrades are estimated
at $10 million and will be programmed into OWASAs
15-Year Capital Improvements Plan. Under anticipated
rates of growth, these improvements would meet OWASAs
raw water needs until about 2030, when anticipated demands
of 15 mgd will exceed the safe yield of the upgraded
system and the community will become increasingly vulnerable
to drought-related water shortages. Additional raw water
storage capacity will be needed to reduce these risks.
Options include
developing the Jordan Lake water supply; dredging University
Lake; building a new and higher dam at University Lake;
raising the dam at Cane Creek; building a new reservoir
on Sevenmile Creek south of Hillsborough; purchasing
water from another utility, such as Durham; and expanding
the storage capacity of the existing Quarry Reservoir
near the intersection of NC 54 and Bethel-Hickory Grove
Church Road.
OWASA has
determined that increasing its raw water storage capacity
by approximately three billion gallons or more through
the extension of American Stone Companys existing
quarry is the most desirable long term option. When
mining is completed no later than 2030, the extended
quarry would be used to store excess water pumped from
Cane Creek and/or University Lake and would be connected
to OWASAs existing Quarry Reservoir.
This paper
presents further details and background information
supporting OWASAs selection of the extended stone
quarry as its preferred future water supply alternative.
Topics include the estimated rates of growth and associated
water demand for the next 50 years; opportunities to
manage demands through water conservation; estimated
safe yield available through additional stone quarry
storage capacity; costs and benefits of alternative
water supply sources; and the relationship between the
proposed quarry extension and the need for Jordan Lake
water.
Tradition of Excellence
A communitys
water supply is one of its most precious resources
a value that the people of Carrboro, Chapel Hill, and
Orange County have recognized through an extraordinary
record of water supply planning, development, and protection.
Stimulated by water shortages of the 1970s and 80s and
fostered by the participation of forward looking representatives
of an active and enlightened citizenry, Carrboro, Chapel
Hill, and Orange County are rightfully proud of the
water supply future they have helped secure.
It is against
this backdrop of public awareness and active involvement
that OWASA presents its water supply vision for the
next 50 years and asks the community to sustain its
exemplary tradition of water supply stewardship.
Community Growth and Future Water Demands
Existing
System: OWASAs water comes from
two sources: the Cane Creek Reservoir, a 3 billion gallon
(bg) impoundment located eight miles west of Carrboro,
and University Lake, a 0.45 bg reservoir located on
Jones Ferry Road just outside of Carrboro. A 0.20 bg
Quarry Reservoir west of Carrboro is available as a
backup water source, and an allocation of Jordan Lake
storage capacity may provide up to 10 million gallons
per day (mgd) for future use. Further information about
these and other potential supply sources are provided
later in this report.
| Historic
Demands: When OWASA began operating
in 1977, annual average raw water demands were approximately
4.5 mgd, which exceeded the estimated safe yield
of University Lake, the only supply source available
at that time. OWASA currently with- draws an average
of 9 mgd from the Cane Creek/University Lake/Quarry
Reservoir system. Future use, which is discussed
more fully below, is expected to double reaching
an annual average of nearly 19 mgd, with summertime
peaks of more than 30 mgd by 2050. A summary
of annual average raw water use since 1977 is presented
in Figure 1. |
|
|
| Future
Demand Forecasts: Through its Comprehensive
Water and Sewer Master Plan, OWASA recently developed
water demand forecasts for the next 50 years. It
is important to note that none of the projection
data or local planning efforts of Carrboro, Chapel
Hill, Orange County, or of the University/UNC Hospitals
extend beyond 2025 or 2030, and that long-term growth
rates and eventual buildout scenarios are not well
established. OWASAs forecasts are based on
the best information and professional judgment available.
The following assumptions underlie all of the forecasts: |
- OWASAs long-term
service area, which is defined as the Urban Services
Area delineated by the Carrboro-Chapel Hill-Orange
County Joint Planning Agreement, will remain unchanged
during the 50-year planning period.
- Future demands will continue
to be determined by retail water sales within the
Urban Services Area. The demand forecasts do not anticipate
any retail or wholesale delivery outside of this service
area.
- Demand forecasts are based
on linear extrapolations of historical housing, employment,
and development trends. The moderate growth rates
experienced during the past 20 to 25 years are expected
to continue.
- Due to the limited amount
of land available for future growth and development
under the existing plans and policies of Carrboro
and Chapel Hill, OWASAs service area will likely
be "built out" sometime within the 50-year
planning period, but neither the timing nor rate of
this is known.
Details of
the demand forecasting methodology are presented in
two technical memoranda (TMs) prepared for OWASAs
Master Plan: TM 3.1 Water Demand Fore-casts (June
18, 1999) and TM 3.2 Baseline and Alternative
Water Demand Forecasts (August 27, 1999).
| Future
forecasts were based on the disaggregation of
water use among five principle customer sectors:
single family residential, multifamily residential,
University/UNC Hospitals, commercial, and irrigation-only
accounts. The relative demand by each of these
sectors is shown in Figure 2. An analysis of
seven years of OWASA customer records indicated
an average daily consumption of 199 gallons
per day (gpd) per single family residence, 137
gpd per multi-family residence, 180 gpd per
1,000 gross square foot (gsf) of University/
UNC Hospitals space, 77 gpd per non-University/UNC
Hospitals employee, and 2,073 gpd per irrigation-only
account. |
|
|
| Future
demands were then estimated by multiplying these
factors by the number of units expected to exist
in each category at ten-year intervals out to
the year 2050. For example, single family residential
demands for the year 2020 were developed by
multiplying 199 gpd by the number of single
family homes projected for that year. This process
was applied to each of the five demand sectors
in ten-year increments. |
Building
and employment estimates were based on an analysis of
data in OWASA's service area since 1977, with residential
growth based on an extrapolation of housing trends observed
from 1990 through 1997. These data indicated growth
rates of 343 new single family and 132 multi-family
units per year within the Carrboro/Chapel Hill service
area. In the absence of any predictors that these rates
will change in the coming years, they were assumed to
remain constant throughout the 50-year planning period.
Similar analyses were conducted for the University/UNC
Hospitals, commercial, and irrigation-only account sectors.
Alternative
high and low demand estimates were developed on the
basis of statistical variations in the historical growth
and water consumption data. The high, low, and expected
estimates were then modified slightly to account for
hot/dry and cool/wet weather conditions. The resulting
forecasts are reported in TM 3.2 Baseline and
Alternative Demand Forecasts, as noted previously.
The underlying
prediction parameters for future water use are summarized
in Table 1, and the resulting projections are presented
in Figure 3. Because the demand forecasts were based
on an extrapolation of historic growth and unit consumption
data, the distribution of demand among the major user
categories in 2050 is not predicted to differ substantially
from the present day pattern illustrated in Figure 2.
Varying the assumptions and input parameters (Table
1) will, of course, produce different future demand
distributions.
Table
1.
Model Parameters Used to Generate Raw Water
Demand Forecasts Under the "Expected Growth"
Scenario |
|
User Category
|
Units
1
|
Base
Year Value
|
Rate
of Increase Per Year
|
Base
Year
|
Water
Use Per Unit (gpd) 2
|
| SF
Residential |
SF
Homes
|
11,669
|
343
|
1997
|
199
|
| MF
Residential |
DUs
|
13,855
|
132
|
1998
|
137
|
| UNC/UNC
Hospitals |
GSF
x 1,000
|
12,670
|
217
|
1997
|
180
|
| Commercial/Other |
Employees
|
13,273
|
408
|
1995
|
77
|
| Irrigation-Only
Accounts |
Accounts
|
50
|
0
|
1998
|
2,000
|
- SF = Single
Family MF = Multifamily DUs = Dwelling Units
GSF = Gross Square Feet of total building
space
- Numbers
in this column represent finished (treated)
water billed to customers, which is approximately
17% less than the total amount of raw (untreated)
water used to produce it.
Raw
Water Pumped to Plant = Total Finished Water
Produced at Plant + Discarded Process Water
Where:
Total Finished Water Produced at Plant =
Billed Water + Unaccounted-for Water
Billed
Water = 0.91 x Total Finished Water Produced
at Plant
Unaccounted-for
Water = 0.099 x Billed Water
Discarded
Process Water = 0.06 x Raw Water Pumped
to Plant
Conversion:
Raw Water Pumped to Plant = 1.169 x Finished
Water Billed to Customers
|
How
Realistic Are These Demand Forecasts?
Long-term growth forecasts especially
for a period that extends beyond the planning
horizon of the local jurisdictions in the service
area are inherently subject to numerous
uncertainties, many of which cannot be quantified
or even identified at this time. It is notable
that the 0.182 mgd/yr expected increase in demand
is less than the 0.221 mgd/yr rate observed
during the 23 years that OWASA has been in operation,
as shown in Figure 3.
|
|
|
Future water use will reflect the complex interaction
of personal choices, public policies and regulations,
as well as constantly changing demographic and
economic conditions during the next 50 years.
OWASA believes that these forecasts represent
the most realistic and reliable estimates of
future water use that can be supported by the
information and professional judgment available
at this time. It will be necessary to periodically
monitor and adjust, as appropriate, the many
variables and assumptions on which these forecasts
are based.
|
Opportunities
to Manage Demands through Water Conservation
One source
of uncertainty in forecasting future demands is the
potential reduction through conservation practices.
Technical Memorandum 3.3 Long-Term Water Demand
Forecasts with Conservation (January 24, 2000), developed
for the OWASA Master Plan, provides a preliminary assessment
of water conservation possibilities. However, most of
the assumptions on which the analysis was based remain
untested in OWASAs service area. TM 3.3 contains
the following consultant disclaimer (the italicized
emphasis appears in the original text): "Recognizing
there is a degree of uncertainty associated with assumptions
used in this analysis, it is premature to rely on the
findings of this TM as a definitive resource for planning
future water and sewer facility requirements for the
OWASA service area."
Nevertheless,
OWASA believes that TM 3.3 provides a valuable preview
of potential water savings through active and passive
conservation programs, and remains committed to collecting
additional data that will help validate or modify the
assumptions applied to future demand forecasts.
Conservation
Findings: Figure 4 provides a graphic
summary of end-use water consumption by OWASA customers.
It is notable that more than 50 percent of the water
is used through indoor plumbing fixtures (toilets, showers,
sinks, and baths) and appliances (washing machines and
dishwashers). Although outdoor uses (swimming pools,
lawn and garden irrigation, and car washing) contribute
substantially to short duration summertime peak demands,
only about 9 percent of OWASAs total annual water
production is used outdoors.
Carrboro-Chapel
Hill is a relatively water-efficient community,
as illustrated by the moderate residential use
in both single and multifamily homes. Average
residential consumption, which is derived by
combining OWASA customer account data with single
and multifamily Census figures, is about 75
gallons per person per day. According to TM
3.3, "this is indicative of a residential
community with conservation water use patterns."
TM 3.3 found that improved plumbing efficiency
achieved in new construction and through the
routine replacement of aging fixtures and appliances
may offer substantial water savings over the
next 50 years. Such changes are referred to
as passive conservation because they are expected
to occur without further intervention by OWASA
or other outside agencies. TM 3.3 indicates
that passive conservation may reduce the 2050
demand forecasts reported above by as much as
18 percent.
|
|
|
By contrast, active conservation programs, such
as toilet replacement incentives, residential
retrofit kits, conservation rates, water use
audits, and individual metering of new multifamily
housing units, are only expected to reduce 2050
demands by less than 2 percent. This is due
to the relatively small amount of OWASA water
used for outdoor purposes, and also reflects
the passive water savings that will eventually
accrue without the initiation of active programs.
Active programs do, however, offer proportionally
greater short term savings by accelerating the
implementation of certain practices, such as
low flow plumbing fixtures, that would otherwise
occur more slowly through "natural"
replacement. Such nearer term savings might
defer the need to upgrade OWASAs raw water
conveyance facilities, described later in this
report, until after 2010. |
Except for
the individual metering of new multifamily housing units,
TM 3.3 found the benefit-cost ratios of active conservation
to be less than 1.0, which means that implementation
costs would exceed the economic savings of those active
programs - even when the cost savings realized through
the deferral of major capital projects, such as water
and wastewater treatment plant expansions, are taken
into account.
Figure
5 illustrates the conservation opportunities
that may be available through the full implementation
of active and passive demand management programs.
|
|
|
What Does This Mean for OWASA?
OWASA believes that active conservation programs,
such as toilet rebates, residential retrofit
kits, water use audits, and conservation rate
incentives, offer potential opportunities to
reduce short duration seasonal peaks, which
significantly affect OWASAs ability to
meet summertime demands. Such programs may also
delay the need to begin expensive capital improvements
to the raw water conveyance system, but active
conservation programs offer little overall reduction
in long term demands. OWASA plans to implement
conservation rate incentives in the near future
and will seriously evaluate the other active
programs recommended in TM 3.3. |
OWASA recognizes
that significant passive water savings may eventually
accrue through the continued implementation of national
plumbing standards that went into effect in 1994, but
OWASA does not intend to incorporate these potential
savings into future raw water demand forecasts until
actual conservation effects can be observed and verified
in local customer data. OWASA is committed to an ongoing
program of data collection and analysis that will enable
the detection of such trends, which can then be used
to modify unit use and other assumptions that comprise
the demand forecasting model.
OWASA simply
doesnt know at this time what effects water conservation
will have on long term demands. Conservation may allow
the deferral of certain capital projects, such as raw
water conveyance improvements, for several years or
more but we cant be sure right now. The
potential reduction in future demands from water conservation
remains one of the important uncertainties challenging
the 50-year forecasts.
Is OWASA Overestimating Its Long-Term Water
Needs?
We don't
think so. OWASA believes that the demand forecasts developed
in TMs 3.1 and 3.2 fulfill their intended purpose of
providing the planning basis for the Comprehensive Water
and Sewer Master Plan, and that the 50-year forecasts
generally conform to the local buildout estimates of
Carrboro and Chapel Hill, which do not look beyond the
2025 planning horizon. OWASA believes that the demand
forecasts are consistent with conservative and responsible
planning principles that seek to preserve multiple options
for future generations of water users. These are the
same principles that Carrboro, Chapel Hill, and Orange
County have applied in protecting the long-term quality
of the Cane Creek and University Lake water supplies.
The future
is difficult to see with clarity, but OWASA firmly believes
that the costs of underestimating future water demands
far exceed the costs of overestimating them.
Capacity of OWASAs
Existing Raw Water System
Existing
System: OWASAs existing system consists
of University Lake, the Cane Creek Reservoir, and the
Quarry Reservoir, as summarized in Table 2 and Figure
6.
Raw water
from University Lake is pumped to the Jones Ferry Road
Water Treatment Plant in Carrboro. Cane Creek water
can either be pumped directly to the treatment plant
or into Phils Creek near the existing Quarry Reservoir,
where it flows downstream to University Lake for repumping
to the treatment plant; or, Cane Creek water can be
pumped into the existing Quarry Reservoir and stored
for later use. Water pumped out of the Quarry Reservoir
can only be conveyed to the treatment plant via Phils
Creek and University Lake.
| Table
2. Characteristics of Existing OWASA Supply
Sources |
University
Lake |
Cane
Creek |
Quarry
Reservoir |
|
Year
Developed
|
1932
|
1989
|
1979
|
|
Drainage
Area (square miles)
|
30
|
31
|
<0.1
|
|
Total
Volume (bg)
|
0.57
|
3.01
|
0.20
|
|
Usable
Volume (bg)
|
0.45
|
2.98
|
0.20
|
|
Surface
Area at Full Volume (acres)
|
212
|
500
|
10
|
|
Average
Inflow (mgd)
|
18.9
|
20.1
|
<0.1
|
|
Minimum
Release Requirements (mgd)
|
None
|
0.14
1.9
(depends on inflow)
|
None
|
Safe
Yield: An important element of OWASAs
Water and Sewer Master Plan has been the accurate determination
of how much water the existing Cane Creek/University
Lake/Quarry Reservoir system can reliably supply. The
yield of a reservoir system is determined by inflows,
outflows, and storage volume of the system. Safe yield
refers to the demand that can be met under specified
operating conditions. For example, a 30-year safe yield
is the demand that a system can reliably support under
low flow (drought) conditions that would occur on an
average of once every 30 years, or have a chance of
about one in 30 of occurring in any given year.
Analyses
reported in TM 5.1 OWASA Raw Water Supply Facilities
Safe Yield Analysis (July 30, 1999) indicated that the
30-year safe yield of the existing raw water system
is approximately 11.2 mgd. The system is presently constrained
by certain limitations on the ability to pump and transmit
water from University Lake, Cane Creek, and the Quarry
Reservoir to the treatment plant. Increasing the capacity
of raw water pumps and transmission mains can increase
the 30-year safe yield of the storage system to about
15.1 mgd, which would represent the maximum practical
use of the University Lake/Cane Creek/Quarry Reservoir
system.
Phase
I Improvements: These conveyance upgrades
are estimated to cost $10 million and will be programmed
into OWASAs 15-Year Capital Improvements Plan
in time to meet the increase in demands that are projected
to occur by 2010 when average day demands are expected
to exceed the present systems 11.2 mgd safe yield.
Additional water provided through the conveyance improvements
would then meet raw water needs until about 2030, when
average day demands are expected to exceed the 15.1
mgd safe yield of the upgraded system. As noted, this
would represent the maximum practical use of OWASAs
existing reservoir and quarry system.
Options
for Meeting Longer Term Needs
OWASA has
explored a range of Phase II alternatives for meeting
demands beyond the 15.1 mgd safe yield of the improved
reservoir/quarry system. These are described briefly
below, with Table 3 providing a comparative summary
of the advantages and disadvantages of each. Additional
details are available in Master Plan TM 5.2 Planning
Level Economic Evaluation of Raw Water Supply Options
(September 9, 1999).
In the following
discussion and in Table 3, safe yield and marginal cost
estimates for each alternative are compared to the existing
reservoir/quarry system assuming that the $10 million
conveyance upgrades have already been completed and
the system safe yield has been increased to 15.1 mgd.
All costs are expressed in 1999 dollars.
Increase
Stone Quarry Storage Volume to 1.0 Billion Gallons:
This option assumes that OWASA can acquire American
Stones existing (active) quarry located west of
Bethel-Hickory Grove Church Road and convert it to a
storage reservoir. OWASA has no rights to this property
except under terms of the existing agreement with American
Stone and the Philip Durham family, which is contingent
on the approval of Carrboro, Chapel Hill, and Orange
County to extend the quarry east of Bethel-Hickory Grove
Church Road.
As of February
2000, the usable storage volume of the quarry pit was
approximately 0.9 bg. One billion gallons of storage
would add 2.2 mgd of capacity to OWASAs raw water
system, providing a total system safe yield of 17.3
mgd, which is less than the 18.6 mgd demand currently
forecast for 2050.
The $8.25/gpd
of additional yield marginal cost of this option, which
is among the highest of those evaluated, is driven largely
by the need for a deepwater intake structure with high
lift pumping and transmission capacity. The marginal
cost estimate also assumes that OWASA could acquire
the property under the low-cost terms of the existing
agreement with American Stone and the Durham family.
Additional expenditures for property would further increase
the cost of this option.
Increase
Stone Quarry Storage Volume to 3.0 Billion Gallons:
Up to 3 bg of additional storage volume could be developed
if the proposed quarry extension is approved. The existing
agreement with American Stone and the Durham family
does not guarantee a specific volume when the enlarged
quarry pit is eventually conveyed to OWASA, but 3 bg
is expected. The agreement does specify that this transfer
will occur no later than 2030.
The 0.9 bg
storage volume of the present pit west of Bethel-Hickory
Grove Church Road is increasing at a rate of 0.05 to
0.10 bg per year, depending on American Stones
production activity and the elevation from which new
rock is removed. If production continues at this rate,
an additional 1.5 to 3.0 bg of storage could be created
by 2030 for a total final volume of 2.4 to 3.9 bg. As
reported in TM 5.2, 3.0 bg of total quarry storage volume
would provide 5.4 mgd more capacity to OWASAs
raw water system, providing a total system safe yield
of 20.5 mgd, which would likely meet the projected 2050
need of 18.6 mgd.
Due to economies
of scale in developing the deepwater intake structure
and high lift pumping capacity, the $3.89/gpd of safe
yield marginal cost of this option is less than half
the cost of the 1.0 bg option described above.
TM 5.2 estimated
the safe yields and marginal costs associated with a
wider range of quarry volumes than the two scenarios
(1 bg and 3 bg) summarized here. For example, 2 bg of
quarry storage volume would provide an additional 3.8
mgd of capacity for a system total system safe yield
of 18.9 mgd, which would likely meet the 2050 raw water
demand forecast. The marginal cost of a 2 bg quarry
was calculated to be $5.12/gpd of additional safe yield.
Dredge Accumulated
Sediment from University Lake:
A study done
for OWASA by Bisesi and Paull in 1991 estimated that
University Lake has lost about 20 percent of its original
storage volume due to sedimentation. Most of this is
believed to have occurred soon after the lake was impounded
during the 1930s when much of the watershed was under
intensive agricultural cultivation. The dredging option
would consist of removing enough sediment from the upper
portions of the lake to add about 0.12 bg of storage
capacity, increasing the usable volume to about 0.57
bg. Because the University owns University Lake and
the surrounding land, OWASA would have to obtain University
and possibly Council of State permission to implement
the dredging.
This option
would yield only 0.2 mgd of additional capacity at a
marginal cost of about $66.40 per gpd of increased yield.
This option represents the highest cost and lowest yield
of all the expansion options considered. Costs would
be higher if sediment analyses revealed toxicity. Dredging-induced
turbidity might require that the lake be taken out of
service during the operation.
Expand University Lake by Building a New and Higher
Dam
Expanding
University Lake would require the construction of a
new dam on Morgan Creek about 400 feet downstream of
the current structure. The water surface elevation would
be 22 feet higher than the lakes current elevation.
This option would include the relocation and/or improvement
of several roadways, including three bridges and other
structures, and would flood 265 acres of additional
land. Additional property acquisition would probably
be necessary. Environmental impacts would be significant.
Because the
University owns University Lake and the surrounding
land, OWASA would have to obtain permission from the
University and the Council of State, as well as other
regulatory agencies. Construction of a new dam would
likely require both state and federal Environmental
Impact Statements (EISs). Regulatory approvals, project
design, land acquisition, and construction would likely
take 10 years or more to complete.
Expand
Cane Creek Reservoir by Raising the Dam
Cane Creek
Reservoir could be expanded by modifying the dam to
raise the water surface elevation 20 feet above its
present level, approximately doubling the usable storage
volume to a total of 6 bg. This would require the relocation
and/or improvement of several roadways, including two
bridges, and would flood an additional 210 acres of
surrounding farmland and woodland. Additional property
acquisition would probably be necessary. Environmental
impacts would be significant.
The project
would likely require both state and federal EIS documents.
Regulatory approvals, project design, land acquisition,
and construction would probably take 10 years or more
to complete. Litigation might impose additional delays.
Expanding
Cane Creek Reservoir by raising the existing dam 20
feet would provide 5.4 mgd of additional capacity at
an estimated marginal cost of $7.39 per gpd of increased
safe yield.
Construct
a New Reservoir on Sevenmile Creek South of Hillsborough
This option,
which was analyzed by Hazen & Sawyer in 1987, would
impound Sevenmile Creek, a tributary to the Eno River
with about 14 square miles of drainage area. More than
400 acres of bottomland would be flooded, requiring
the relocation of several roads and residences. Because
the watershed contains portions of the Interstate 85
and US 70 highway corridors, long term water quality
protection would be substantially more problematic than
for the University Lake and Cane Creek supply sources.
This project
would require OWASA to acquire or obtain access to land
purchased previously by Orange County for a possible
reservoir on Sevenmile Creek. Additional private land
would also have to be acquired. This option would require
an interbasin transfer certificate from the North Carolina
Environmental Management Commission as well as state
and federal EIS documents. As with the University Lake
and Cane Creek Reservoir expansion options, regulatory
approvals, project design, land acquisition, and construction
would probably require 10 years or more to complete.
Litigation could impose additional delays.
A new reservoir
on Sevenmile Creek would provide OWASA with 4.9 mgd
of additional water supply capacity at a marginal cost
of about $8.72 per gpd of increased safe yield. Environmental
impacts would be significant.
Develop
Jordan Lake Water Supply Allocation
This option
would include the construction of a water supply intake
near the western shore of Jordan Lake south of US Highway
64, two pumping stations, and a raw water transmission
line to OWASAs Jones Ferry Road Water Treatment
Plant in Carrboro. For this analysis, it was assumed
that OWASA would pay all costs for full use of the its
Jordan Lake water supply storage allocation.
This could
provide 10 mgd of additional capacity for an estimated
marginal cost of $2.99 per gpd of increased safe yield.
Cost-sharing with potential partners, such as Chatham
County or Durham (City), might lower these costs. OWASA
could develop its Jordan Lake allocation with minimal
disruptions or environmental impact, but state and federal
EIS documents would probably be required.
Analytical
data from the past 11 years indicate that water quality
in Jordan Lake is good and nearly indistinguishable
in quality from other Triangle area water supply reservoirs,
except in the northernmost section upstream of S.R.1008,
where the water is highly enriched with nutrients. The
Jordan Lake watershed is nearly 30 times larger than
the combined drainage area of University Lake and Cane
Creek Reservoir. Most of this lies outside of Orange
County.
Purchase
Water from Other Suppliers
Wholesale
purchases of treated water from another supplier, such
as Chatham County or Durham (City), would involve no
environmental impacts, but would subject a portion of
OWASAs water supply to contractual terms negotiated
with another entity. Because no arrangements for guaranteed
water sales to OWASA are currently in place or under
negotiation, information is not available about additional
capacity or marginal costs of this option.
No
Action to Secure Additional Long Term Supplies
The "no
action" alternative would involve no costs and
have no environmental impacts.
Current forecasts
indicate that average day raw water demands will equal
the 15.1 mgd safe yield of OWASAs upgraded reservoir
and quarry system by about 2030. It is not possible
to know how future leaders will choose to meet the water
demands of their time if no further actions are taken
to provide for the communitys long term needs.
Preferred Option
Increase Stone Quarry Volume to 3 Billion Gallons
Figure 7. Proposed Quarry
Extension Across Bethel-Hickory Grove Church Road
OWASA believes
that the proposed quarry extension across Bethel-Hickory
Grove Church Road is the most desirable option for providing
additional water when future demands exceed the supply
available from the Phase I improved Cane Creek/University
Lake/Quarry Reservoir system. Three billion gallons
of quarry storage volume would provide a total system
safe yield of 20.5 mgd, which would likely meet the
demands currently projected for 2050 (Figure 8). OWASA
recognizes that the existing agreement with American
Stone and the Philip Durham family does not guarantee
a specific usable storage volume when quarry operations
end, but OWASA will make every effort to acquire a total
quarry storage volume of at least 3 billion gallons.
The marginal
cost of the 3 bg quarry option is less than half the
cost of the other expansion alternatives except for
Jordan Lake, which is about 30 percent less than the
quarry extension. OWASA prefers the quarry to Jordan
Lake because of the greater degree of local control
over future water quality. The total drainage area of
the Cane Creek/University Lake/Stone Quarry system is
approximately 61 square miles, of which 90 percent lies
within Orange County and is subject to local source
water protection requirements that are among the most
stringent in North Carolina. By contrast, Jordan Lake
drains an area of approximately 1750 square miles, nearly
30 times larger than OWASAs local watersheds,
and is more susceptible to contamination from certain
pollutants, such as MTBE, than University Lake or Cane
Creek. Unlike Falls Lake, which is another Corps of
Engineers reservoir of comparable size, Jordan Lake
has not yet been the subject of a comprehensive watershed
protection study, and no coordinated management program
is currently in place.
Because
of the high projected costs, significant environmental
impacts, and the likelihood of protracted and
contentious legal/regulatory difficulties, OWASA
does not intend to pursue either the University
Lake or Cane Creek expansion options, nor will
OWASA seek to develop a new reservoir on Sevenmile
Creek. By contrast to such high impact projects,
the quarry extension represents the continuation
of an existing activity with little or no additional
effect on the nearby community and no significant
impact on the natural environment. Rather than
flooding hundreds of acres of woodland, farmland,
and wildlife habitat, the quarry extension will
disturb less than 30 acres of property that
is already owned by either OWASA, American Stone,
or the Philip Durham family. When quarry operations
are completed and the pit has been converted
into a storage reservoir, more than 100 acres
of barren land currently used for quarry and
asphalt plant operations will be restored and
revegetated, providing a green buffer around
a reservoir that may be as large as 60 acres.
|
|
|
OWASA believes
that the quarry extension is the preferred alternative
for meeting the long term water supply needs of its
customers.
Additional
Storage Volume Additional Benefits
Although
it might be possible to meet forecasted 2050 demands
with only one or two billion gallons of additional storage
capacity, larger volumes offer important intangible
benefits. These include:
Additional
security for an uncertain future: As noted earlier,
OWASAs 50-year demand forecasts are subject to
substantial uncertainty. We believe that the additional
safe yield gained from more storage capacity represents
a reasonable safeguard for the future.
One of the
main reasons that OWASA, Carrboro, Chapel Hill, and
Orange County supported large lot zoning to protect
the quality of Cane Creek and University Lake was the
recognition that if a less conservative approach were
adopted and subsequently failed, such as higher density
development with extensive structural stormwater controls,
it would never be possible to go back and "undevelop"
the watershed to correct the water quality damage.
OWASA believes
that a similarly conservative approach is appropriate
for assuring the future quantity of water available
from these same supplies. OWASA continues to believe
that it is preferable to err on the side of overestimating
future water needs especially when the social,
economic, and environmental costs of additional quarry
capacity are low.
Reduced
drawdowns of University Lake and Cane Creek:
Additional storage capacity and the corresponding increase
in safe yield will reduce the extent and frequency of
lake level drawdowns as water use continues to grow.
Benefits to the aesthetic and recreational value of
University Lake and Cane Creek would be substantial,
as well as environmental benefits to fish, wildlife,
and habitat protection.
More
reliability and "drought-proofing" for the
future: Additional storage capacity will
increase the ability of the raw water system to sustain
community needs under more severe drought conditions.
Safe yield options discussed in this report represent
demands that could be supported under drought conditions
that occur approximately once in 30 years. Additional
quarry volume would help meet community demands under
more stringent conditions, such as the 1976-77 drought,
which was the most severe in the 72-year record.
Increased
operational flexibility and reliability:
Additional water supply capacity will provide more operating
flexibility if one of the reservoirs must be taken out
of service due either to an emergency or for scheduled
maintenance of the dam, intake, structure, or the raw
water pumping and transmission facilities.
Additional
water available for downstream release:
Within the 50-year planning period, it is likely that
regulatory agencies will determine that the maintenance
of water quality in Morgan Creek requires supplemental
releases from University Lake, where no minimum streamflow
requirements currently exist. Additional storage volume
in OWASAs reservoir/quarry system would help offset
the resulting loss in safe yield.
Sustainable
resource management: A key principle of
sustainability is to manage resources today in ways
that maintain a full range of opportunities for future
generations. Maximizing the yield of OWASA's raw water
system through increased quarry volume can achieve this
at little or no cost in community resources.
Optimizing
local and regional water resources: Stone
quarry extension offers the best opportunity to maximize
the yield of OWASA's existing watersheds without developing
a new supply source. One result would be less future
reliance on Jordan Lake, which will likely become more
important to other communities in the growing Triangle
Area. Sufficient capacity will reinforce OWASAs
role as a key player in the regional water supply picture.
Other
Questions?
Will
Jordan Lake still be needed? With the
20.5 mgd system safe yield provided by 3 bg of quarry
capacity, it is unlikely that OWASA will have to rely
on Jordan Lake to meet its water supply needs during
the next 50 years. This is not to suggest that OWASA
should relinquish its storage allocation or the 125
acres of property at it owns Jordan Lake, which represent
valuable assets in which customers have invested more
than $600,000 since 1988. It may be possible to convert
or exchange these resources for valuable utility services,
perhaps through a Jordan Lake partnership with other
entities.
How
soon after quarry operations have ended could OWASA
begin using the vacant pit for water storage?
A number of regulatory, design, construction, and implementation
activities would have to be completed before the vacated
quarry could be used for water storage. Overall, it
is estimated that the quarry could be put into operation
as a water storage reservoir within three to six years
after the mining is completed.
How
do we know that the quarry will hold water without leaking?
Even though OWASAs existing Quarry Reservoir has
retained water since it was filled 20 years ago, OWASA
recently commissioned a geological consulting firm to
examine American Stones active quarry operation
west of Bethel-Hickory Grove Church Road and OWASAs
existing Quarry Reservoir. The consultants did not find
any structural evidence, such as fractures, fissures,
permeable overburden, and so forth, to indicate that
the quarry would leak when filled with water. The only
elevation constraint appears to be topographic; i.e.,
the overflow or rim elevation of the pit, which is approximately
490 feet above sea level.
Are
there any special water quality concerns about storing
lake water in such a deep quiescent reservoir?
Due to the extreme depth and long detention times, water
stored in an expanded quarry reservoir is expected to
have fewer nutrient, algae, and total organic carbon
(TOC) problems and pose fewer treatment challenges than
water withdrawn directly from University Lake or Cane
Creek Reservoir. In addition, lakewater diverted to
the quarry reservoir will have undergone a certain degree
of "natural" pretreatment through biological
and physical processes in the lake, resulting in lower
turbidity and nutrient concentrations (but not necessarily
lower TOC) than in tributary water flowing into the
lakes themselves. The degree of this pretreatment would
vary seasonally, depending on when water was diverted
into the enlarged quarry reservoir.
Why
do we need to do anything now if our existing supplies
will last until 2030? The Carrboro-Chapel
Hill-Southern Orange County community is recognized
statewide for its proactive stewardship of environmental
resources. In no area has this been more evident than
local efforts to protect the long term quality of the
Cane Creek and University Lake water supplies
efforts that were made with the expectation that these
sources will supply water to the community for the next
100 years. It was also understood that the water quality
benefits of the protective actions taken today would
not be fully realized for many years to come.
OWASA believes
that the same values that have guided the communitys
water quality protection accomplishments should be applied
to assuring an adequate quantity of water for the future.
Are
there any other related issues we should be concerned
about? Some nearby residents of the quarry
have expressed concerns about nuisance noise, traffic,
well problems, and property values, as well as possible
health effects related to silica dust and radon emissions
from American Stones existing quarry operation.
OWASA is addressing these issues through a separate
supplement to an Environmental Impact Statement (EIS)
that was originally prepared in 1993. The principal
finding of the draft document is that "The proposed
project appears to pose no significant threat to human
health, safety, or natural resources. No evidence of
past or present significant threats to health from silica
dust, radon, traffic impacts, or water quality could
be identified through the research conducted under this
study" (emphasis added).
The final
EIS Supplement report will be completed and provided
to the public by mid-March 2000.
Summary and Conclusions
OWASA currently
withdraws an average of 9 million gallons per day (mgd)
of water from the Cane Creek/University Lake/Quarry
Reservoir system. Customer demands are expected to exceed
the raw water systems safe yield of 11.2 mgd by
2010. The present reservoir/quarry system receives sufficient
streamflow and has enough storage capacity to support
an average yield of 15 mgd, but is presently constrained
by limitations of the infrastructure to move additional
raw water from the reservoirs to the Jones Ferry Road
Water Treatment Plant in Carrboro.
The present
safe yield can be increased to 15 mgd through improvements
to the conveyance system, such as larger raw water transmission
pumps and pipelines from University Lake and Cane Creek
to the treatment plant. Costs for these upgrades are
estimated at $10 million and will be programmed into
OWASAs 15-Year Capital Improvements Plan. Under
anticipated rates of growth, these improvements would
meet OWASAs raw water needs until about 2030,
when anticipated demands of 15 mgd will exceed the safe
yield of the upgraded system and the community will
become increasingly vulnerable to drought-related water
shortages. Additional raw water storage capacity will
be needed to reduce these risks.
OWASA evaluated
a number of options for securing additional water after
2030. These include developing the Jordan Lake water
supply; dredging University Lake; building a new and
higher dam at University Lake; raising the dam at Cane
Creek; building a new reservoir on Sevenmile Creek;
purchasing water from another utility, such as Durham;
and expanding the storage capacity of the Quarry Reservoir
near the intersection of NC 54 and Bethel-Hickory Grove
Church Road.
OWASA has
determined that increasing its storage capacity by approximately
three billion gallons or more through the extension
of American Stone Companys existing quarry is
the preferred alternative for meeting the long term
water supply needs of its customers in a manner that
is consistent with the communitys values of environmental
stewardship and sustainable growth. The quarry extension
represents the continuation of an existing activity
with little or no additional effect on the nearby community
and no significant impact on the natural environment.
Prepared
by: _________________________ Approved by:________________________
Edward A.
Holland, AICP Ed Kerwin
Director
of Planning Executive Director
Sources
of Additional Technical Information
CH2M HILL, 1999. OWASA Water
and Sewer Master Plan Technical Memorandum
3.1 Water Demand Forecasts, June 18, 1999.
CH2M HILL, 1999. OWASA Water
and Sewer Master Plan Technical Memorandum
3.2 Baseline and Alternative Water Demand Forecasts
August 27, 1999.
CH2M HILL, 2000. OWASA Water
and Sewer Master Plan Technical Memorandum
3.3 Long-Term Water Demand Forecasts with Conservation,
January 24, 2000.
CH2M HILL, 1999. OWASA Water
and Sewer Master Plan Technical Memorandum
5.1 OWASA Raw Water Supply Facilities Safe Yield
Analysis July 30, 1999.
CH2M HILL, 1999. OWASA Water
and Sewer Master Plan Technical Memorandum
5.2 Planning Level Economic Evaluation of Raw
Water Supply Options, September 9, 1999.
CH2M HILL, 1999. Memorandum
to Orange Water and Sewer Authority. Effect of Stone
Quarry Reservoir Volumes on Cane Creek Reservoir and
University Lake Drawdown Levels, December 14, 1999.
CH2M HILL, 1999. Memorandum
to Orange Water and Sewer Authority. Expected Water
Quality in Expanded Stone Quarry Reservoir, December
27, 1999.
CH2M HILL, 1999. Memorandum
to Orange Water and Sewer Authority. Implementation
Schedule for an Expanded Stone Quarry Raw Water Storage
Reservoir, December 15, 1999.
Orange Water and Sewer Authority,
2000. Staff Memorandum. Water Demand Forecasts and Local
Buildout Projections, October 1, 1999 (Revised January
21, 2000).
Earth Tech, Inc., 1999 Report
to Orange Water and Sewer Authority. Reserve and Hydrologic
Evaluation of OWASA and American Stone Properties, December,
1999.
Hazen and Sawyer, 1987. Orange
County Water Supply Study Phase I.
Tetra Tech, 2000. Report
to Orange Water and Sewer Authority. (Draft) Supplement
to the Environmental Impact Statement Proposal
to Extend the Stone Quarry and Quarry Reservoir Near
the Intersection of NC 54 and Bethel-Hickory Grove Church
Road, February 2000.
|