Burning Tree Drive Water Main Replacement Project
OWASA Contractor: Crossroads Site Development, LLC
Sign up for regular updates about this project here.
About the Project: OWASA is replacing 5,650 feet of aging water main along Burning Tree Drive and two of its side streets, Canterbury Lane and Torrey Pines Place. The project is expected to take up to 12 months to complete. Expected impacts include dust, noise, and limited traffic impacts (single lane closures in active work areas). Working hours will be 7 a.m. to 7 p.m., Monday through Friday. No weekend work is expected.

Latest Update (11/18/26):
The following work is planned for November 18 – December 18:
-Water main and individual property water service line installation on Burning Tree Drive from Pinehurst Drive toward Torrey Pines Place
-Valve installation at intersection of Cleland Drive and Burning Tree Drive
-Temporary asphalt paving on Burning Tree Drive from Pinehurst Drive to Cleland
There will be no construction on November 26 and November 27. All traffic barriers and impacts will be removed.
Please note that the planned work is subject to change based on weather conditions and construction progress.
How this work may affect residents in the area:
Residents will see crews from Crossroads Site Development and their equipment in the neighborhood between the hours of 7 a.m. and 7 p.m., Mondays through Fridays (except Thanksgiving Day and Friday following Thanksgiving). Impacts may include dirt, dust, and noise during work hours.
Traffic, parking, and driveways:
-Single-lane closures will be necessary to perform this work safely, but through traffic will be maintained. Lane closures will only occur between 8 a.m. and 5 p.m., Monday through Friday. No traffic impacts are expected on the weekend.
-Through traffic will be maintained during the valve installation within the Cleland Drive and Burning Tree Drive intersection, but there may be times where turns between Burning Tree Drive and Cleland Drive are briefly restricted.
-Street parking and driveway access may also be temporarily impacted during this work. Crossroad Site Development personnel will attempt to contact you directly if access to your driveway will be affected or if your vehicle needs to be moved from the public right-of-way.
-For your safety and the safety of others, please obey all traffic measures in place during construction and allow extra time when traveling through the neighborhood.
Sediment barriers:
Residents should not disturb the temporary sediment control barriers placed around storm drains and along the work area. These barriers are required by the Town and the N.C. Department of Environmental Quality to help keep construction dirt and debris from washing into storm drains and nearby waterways. Crossroads Site Development will continue to monitor the weather and adjust these barriers as needed. If heavy rain is expected, the barriers may be adjusted or temporarily removed to prevent water from backing up into the street.
OWASA will send monthly updates throughout the project via email. Please make sure your contact information is up-to-date with OWASA by signing up to receive email updates about this project HERE. Thank you for your patience and cooperation as we work to improve the community’s drinking water infrastructure. If you have any questions or concerns, please do not hesitate to contact me.
Project Contact: Mo Rasheed, OWASA Utilities Engineer