Barclay Rd. Water Line Replacement

Work is continuing in the Barclay Road neighborhood as crews are finishing the remaining section of the project.

Construction progress slowed significantly in March and April due to COVID-19 staffing reductions and difficult site conditions, including a section of hard bedrock located between Williams Circle and Martin Luther King Junior Boulevard.

Remaining work to complete the project consists of final connections for the new water main between Williams Circle and Justice Street, project paving, cleanup, and restoration. We expect the project to be complete by the end of June.

Please feel free to contact the project manager listed below if you have any questions or comments and if you would like to receive future updates by e-mail. To sign up for e-mail updates please go to https://tinyurl.com/BarclayRoadWater. Thank you very much for your patience and understanding as we complete this work.

Sincerely,

Coleman Olinger, P.E., Project Manager

Email / 919-537-4249