OWASA contractor Pipeline Utilities began preconstruction in November 2025, and construction began in January 2026. This project is replacing over 18,000 feet of water main in the Ridgefield-Briarcliff neighborhood.
General Information: OWASA’s contractor, Pipeline Utilities, has deployed a second crew, so residents have likely noticed more activity over the last two months. This is allowing for more efficient work but may be more disruptive in the short-term. With each update, we will include an updated map of our progress on the project. Prior to any major change in the type of work being performed (i.e. paving), a notice will be sent with a more detailed schedule, anticipated disruptions, and changes (like signage and road closures). We have also included a document detailing the steps in the water main installation process to clarify why the project tasks proceed in the order that they do.
Planned Work for October 2026:
- Continue water main installation on Churchill Drive from Longleaf Drive toward Leclair Street
- Continue individual water service connections on Tinkerbell Road and Churchill Drive
- Complete water main installation on Emory Drive north of Longleaf Drive
- Begin water main installation along Emory Drive from Longleaf Drive toward Leclair Street
- Connect newly installed water main on Churchill Drive, Longleaf Drive, and Tinkerbell Road to existing water main along Ephesus Church Road on teacher workdays
Please note: Water discoloration can arise from sediment and mineral deposits being dislodged during construction. To avoid discolored water, turn faucets on in your home until the water runs clear. Changes in water pressure can also occur during this work. Residents own and are responsible for their pressure release valve (PRV). If you experience water pressure issues, even after adjusting your pressure release valve, you must address them with a plumber. OWASA and our contractor are not permitted to work on plumbing fixtures inside your home.
This is a 22-month project, expected to be complete by fall 2027. As of September 2026, this project is 50% complete. For more project information, visit the project webpage HERE.

Project Information
Expected impacts to neighborhood customers:
- Noise during working hours (7 a.m. to 7 p.m., Monday – Friday)
- Dust, dirt, & mud
- Reduced lanes of traffic
- Brief (less than two hours) water service disruption when connecting customers to the new line at end of project
Click HERE to sign-up to receive email updates about this project.
- Heavy construction started in early 2026. Construction to replace the water main will be conducted in sections to minimize impacts on the neighborhood. When construction begins, residents will see construction crews and equipment in your neighborhood, and may experience noise, dirt, dust, and mud disturbances. Single-lane road closures on neighborhood roads will be necessary during construction, but through traffic will be maintained. Work times will be from 7:30 a.m. to 7 p.m. Monday through Friday for the duration of construction.
- During the school year, construction near the intersection of Ephesus Church Rd. and Churchill Dr. to Longleaf Dr. will be restricted to 9 a.m. to 1 p.m. and 3 p.m. to 7 p.m.
- Street parking in the neighborhood will be limited during this project. Street parking restrictions will only apply in the section(s) where active construction is taking place. If your vehicle needs to be moved from the public right-of-way, our contractors will contact you directly.
- Brief (less than two hours) water service disruptions will occur during this project when customers’ water service is connected to a temporary water main and again when connected to the new water main. Occasionally, there will be longer water outages (six hours or more) at the final stage of construction in each section, when customers’ water service is permanently connected to the new water main. OWASA will notify customers before their water service is turned off and when it is turned back on.
- Thank you for your patience and cooperation while we work to improve the community’s drinking water infrastructure in your neighborhood. OWASA will continue to update you as this project progresses.
For more information on this project, please contact project manager Darren Berger at dberger@owasa.org.